The 7th Circuit Court of Appeals today reversed a decision out of Indiana regarding a claim by the Environmental Protection
Agency that Cinergy Corp. was wrong to modify its coal-burning plants without first obtaining a permit from the EPA.
In a suit older than a decade, the U.S. District Court for the Southern District of Indiana, Indianapolis Division, had found
in favor of the U.S. government, but the 7th Circuit disagreed in U.S.A. and State of New York v. Cinergy Corporation, et al., Nos. 09-3344, 09-3350, 09-3351.
The EPA had filed suit over permits needed for modifications. At issue was whether the permits were required if the hourly
increase in emissions of nitrogen oxide and sulfur dioxide had not increased, even if the annual amounts had increased due
to more productivity from the modifications, and therefore more hours of production.
The District Court rejected Cinergy’s argument that because the hourly emissions rate hadn’t changed, even if
the annual rate increased, they didn’t need the permit. The 7th Circuit agreed in an interlocutory appeal.
After the 7th Circuit’s decision on the interlocutory appeal, the case continued in the District Court with a jury
trial, “although a case of such complexity, rife with technical issues, is not an ideal one for a jury to decide,”
wrote 7th Circuit Judge Richard A. Posner.
Following the trial, where 14 modification projects at three plants were at issue, the jury found liability with respect
to four of the projects, all at Cinergy’s plant in Wabash and all undertaken between 1989 and 1992.
However, at the time these projects took place, the Indiana standard had not yet been updated to reflect the Clean Air Act.
“The Clean Air Act does not authorize the imposition of sanctions for conduct that complies with a State Implementation
Plan that the EPA has approved. See 42 U.S.C. § 7413(a)(1). The EPA approved Indiana’s plan with exceptions
that did not include Section 43, thinking that Indiana would submit a revised plan which the EPA would then approve. Which
is what happened – only it took 12 years,” Judge Posner wrote.
“The agency’s frustration is understandable,” regarding the EPA, he continued. “It embraced the actual-emissions
standard, which for the reasons explained in our previous opinion and repeated earlier in this one makes better economic sense,
before section 43 was presented for its approval. It should have disapproved it; it didn’t; but it can’t impose
the good standard on a plant that implemented the bad when the bad one was authorized by a state implementation plan that
the EPA had approved. The blunder was unfortunate but the agency must live with it.
“The judgment of the district court must therefore be reversed so far as the sulphur dioxide emissions are concerned,”
he added. “With respect to the emissions of nitrogen oxide, the parties agree that the actual-emissions standard controls,
and the only question we need answer is whether the district court was right to allow the EPA’s expert witnesses to
testify that the modifications made would result in an increase in annual emissions beyond what the state implementation plan
permitted.”
He emphasized the term “would,” as opposed to “did,” because the permit must be obtained before a
modification can be made so the effect on emissions is a prediction rather than an observation, he wrote.
Because the Wabash plant is old, the formula used by the EPA experts to determine emissions based on baseload numbers as
opposed to cycling numbers, would not apply to the Wabash facility because it does not operate at full capacity.
“In fairness to the district judge, we note that Cinergy didn’t argue this point to him with any clarity; this
is a common pitfall in a scattershot approach to litigation. The point isn’t even clear in Cinergy’s appeal briefs,”
Judge Posner wrote.














The court of appeals not only tries to rewrite or interpret the law to suit their fancy, now they choose play stupid as well. Every consideration must be given to pro se litigants, who are not held to the same standards as attorneys, as stated by,SCOTUS. I assume they didn't have a lawyer, since one wasn't mentioned and I strongly suggest thatb the rest of the, origional petitioners get back in there and fight for their rights.
the irony of situations like this is that the clients whom conour cheated are the ones who should be pulling hardest for him to remain free and keep his law license, so they have some hopes of him paying back. really bury the guy deep and then there will be little hope of restitution
Qualified immunity, means that if you wear a badge, you are exempt from law and free to do anything you please! The courts will back badge toting individuals, because they think they are above the law as well. They think, they have judicial immunity, they do not.
Deeply, deeply concerned? I'll bet if it was the judge's money that had been swindled we'd see deep concern with actual consequences. First a Ponzi scheme, then a shell game with the assets…c'mon, hasn't Conour abused the judicial system and his clients long enough? I say enough already.
Wow, just wow.