ILNews

Court: insufficient notice bars tort claim

Back to TopE-mailPrintBookmark and Share

The Indiana Court of Appeals today ruled that insufficient notice barred a complaint for damages in a case involving a condominium complex and its various longtime issues.

In F.B. Boushehry v. City of Indianapolis, et al., No. 49A05-1002-PL-55, F.B. Boushehry appealed the trial court’s grant of summary judgment in favor of the city.

Boushehry had contracted in 1992 to purchase a parcel of land in Indianapolis on which he planned to build a condominium complex. The land was adjacent to a shopping center owned by John and Martha Carmody. The center was connected to a private sewer line built by them and that connected to the nearest public sewer line. The Carmodys’ sewer line ran along Stop 10 Road, which included portions of the land that Boushehry planned to buy.

To be habitable, Boushehry’s condominium complex would be required to connect to a sewer line. One option was to construct his own private sewer line that would connect with the nearest public sewer line directly. Another option was to negotiate the right to connect to the Carmodys’ sewer line, which Boushehry chose to do. Despite various issues including disagreements with the Carmodys about the sewer line, Boushehry bought the land.

Boushehry represented to the city that he would rehabilitate the existing private sewer line, which the city required when he applied for sewer construction and connection permits.

In October 2003, the city issued a stop-work order because of an unlicensed electrical contractor working on the complex without a permit. It also issued two other stop-work orders in November 2003 because a sanitary sewer wasn’t constructed according to a city-approved design and because Boushehry failed to submit a certification of completion and compliance for a storm sewer. The city also determined Boushehry had connected at least four condominium units and discharged waste into the private sewer line, which had not been rehabilitated as required. The city red flagged the complex so no additional permits would be granted until all violations were resolved.

On Nov. 7, 2003, Boushehry filed a complaint for preliminary and permanent injunction and for a writ of mandamus to prohibit enforcement of the city’s October 2003 stop-work order. He later amended the complaint to include all of the city’s stop-work orders. In 2004, Boushehry filed a notice of tort claim pursuant to the Indiana Tort Claims Act and attached his amended complaint to the notice; however, the notice referred only to the initial stop-work order as the basis for his claim. After hearings, the trial court ruled the Carmodys owned the private sewer line; the private sewer line could not handle the increased sewer flow from the condominium complex without first undergoing the required rehabilitation; and the city’s stop-work orders and red flag against the condominium complex were proper and lawful. Boushehry did not appeal this judgment.

However, in 2005, Boushehry filed a complaint for damages that alleged the city from 1992 to 2005 “negligently, tortiously, and erroneously determined that [the private sewer line] is owned by [the Carmodys].” This gave rise to the instant case. Instead of filing a new notice under the act with his 2005 complaint, he relied on his 2004 notice. In 2007, Boushehry amended his complaint to include a claim that from 1992 to the present, the city made false and malicious statements to third parties regarding his ownership of the land.

The city filed for summary judgment in 2009, asserting the claims were barred because of Boushehry’s failure to comply with the act’s notice requirements, the statute of limitations, the doctrine of res judicata, and the defense that the city’s actions were justified. The trial court granted summary judgment in favor of the city Jan. 8, 2010. Boushehry appealed, citing Collier v. Prater, 544 N.E.2d 497, 499 (Ind. 1989).

According to the act’s provisions, a claim against a political subdivision is barred unless notice is filed with the political subdivision within 180 days after the loss occurs.

“Here, however, unlike in Collier, Boushehry’s notice did not give the City any notice of the claims that Boushehry subsequently raised against the City because the claims raised by Boushehry were entirely different from the claim that was identified in his notice. See Lukowiak, 810 N.E.2d at 383-84,” wrote Judge Cale Bradford.

The appellate court concluded Boushehry’s notice was insufficient to notify the city it needed to defend itself against claims ultimately raised in his amended complaint and affirmed the trial court.
 

ADVERTISEMENT

Sponsored by
ADVERTISEMENT
Subscribe to Indiana Lawyer
  1. Affordable Loan Offer (ericloanfinance@hotmail.com) NEED A LOAN?Sometime i really wanna help those in a financial problems.i was wondering why some people talks about inability to get a loan from a bank/company. have you guys ever try Eric Benson lending service.it cost dollars to loan from their company. my aunty from USA,just got a home loan from Eric Benson Lending banking card service.and they gave her a loan of 8,000,000 USD. they give out loan from 100,000 USD - 100,000,000 USD. try it yourself and testimony. have a great day as you try.Kiss & Hug. Contact E-mail: ericloanfinance@hotmail.com

  2. From the article's fourth paragraph: "Her work underscores the blurry lines in Russia between the government and businesses . . ." Obviously, the author of this piece doesn't pay much attention to the "blurry lines" between government and businesses that exist in the United States. And I'm not talking only about Trump's alleged conflicts of interest. When lobbyists for major industries (pharmaceutical, petroleum, insurance, etc) have greater access to this country's elected representatives than do everyday individuals (i.e., voters), then I would say that the lines between government and business in the United States are just as blurry, if not more so, than in Russia.

  3. For some strange reason this story, like many on this ezine that question the powerful, seems to have been released in two formats. Prior format here: http://www.theindianalawyer.com/nominees-selected-for-us-attorney-in-indiana/PARAMS/article/44263 That observed, I must note that it is quite refreshing that denizens of the great unwashed (like me) can be allowed to openly question powerful elitists at ICE MILLER who are on the public dole like Selby. Kudos to those at this ezine who understand that they cannot be mere lapdogs to the powerful and corrupt, lest freedom bleed out. If you wonder why the Senator resisted Selby, consider reading the comments here for a theory: http://www.theindianalawyer.com/nominees-selected-for-us-attorney-in-indiana/PARAMS/article/44263

  4. Why is it a crisis that people want to protect their rights themselves? The courts have a huge bias against people appearing on their own behalf and these judges and lawyers will face their maker one day and answer for their actions.

  5. State's rights, civil rights and human rights are all in jeopardy with Trump in the WH and Sessions running Justice.

ADVERTISEMENT