DTCI: Getting Paid on a Construction Project

Back to TopCommentsE-mailPrintBookmark and Share
drewry Drewry

Most standard subcontracts contain a contingent payment clause that provides that a subcontractor’s payment from a general contractor is contingent upon the GC’s receipt of payment from the owner. Under such a clause, if the owner fails to pay the GC, then payment is neither due nor owing to the subcontractor. Are these enforceable?

From the GC’s perspective, the need to make such payments conditional or contingent upon being first paid by the owner is obvious. The GC does not want to end up being the involuntary financing agent for the project if for some reason the owner delays payment to the GC or withholds payment altogether, especially if the reasons for that withholding are no fault of the GC. In other words, the GC wants to avoid getting “gapped,” where it would find itself in the position of receiving nothing from the owner and having to front the money to pay the subcontractor. From the subcontractor’s perspective, the subcontractor does not want to risk nonpayment due to a contractual relationship upstream to which it is not a party.

Despite being in virtually every GC’s standard subcontract form, there remains uncertainty in the construction industry as to the effectiveness of the clause. A recent Indiana case, however, has once again shed light on its application. This is the case of BMD Contractors, Inc. v. Fidelity and Deposit Company of Maryland, 679 F.3d 643 (7th Cir. 2012).

Distinguishing ‘pay-when-paid’ and ‘pay-if-paid’ clauses

The typical contingent payment provision is one of two types, either providing (1) that payment will not be made until payment is received from the owner (“pay-when-paid”) or (2) that the obligation for payment will not arise at all unless payment is made by the owner (“pay-if-paid”). The latter type of clause is a true contingent payment clause, making performance of a contractual precondition by the owner the predicate for the contractor’s obligation to pay the subcontractor.

A number of cases from other states have upheld contingent payment clauses where the contract between the contractor and the subcontractor contains an express condition clearly showing that it is the intention of the parties that payment to the contractor is a condition precedent to the subcontractor’s right to payment. Courts have upheld such clauses where the parties expressly contemplate shifting the burden of forfeiture under a subcontract to the subcontractor by promising payment only if the primary contractor is paid. Clauses that clearly state the intent to make owner payment a condition precedent are routinely held to be adequate to transfer the risk of nonpayment by the owner to the subcontractor. It is not the use of the word when or if that is dispositive on whether the clause is enforceable but whether there is clear evidence of an intent by both parties to shift the risk of collection altogether. Consequently, to be enforceable as a pay-if-paid clause, a majority of the courts from other jurisdictions have ruled that the term condition precedent must be used in the clause itself.

Absent such definitive language, contingent payment clauses in many other jurisdictions have been interpreted as failing to represent a condition precedent that excuses payment altogether, but rather as constituting a covenant to pay within a reasonable time. In these cases, the courts have held that the contingent payment clause did not create a condition precedent for payment, but established the time and means of payment. In other words, it is a way of deferring the subcontractor’s payment for a reasonable length of time but is not an ultimate bar to recovery. Traditionally, Indiana was among those states interpreting contingent payment clauses this way.

Indiana’s position on contingent payment clauses

Indiana courts first addressed the contingent payment clause in Midland Engineering Co. v. John A. Hall Construction Co., 398 F. Supp. 981 (N. D. Ind. 1975). There, the District Court interpreted a contingent payment clause contained in a subcontract and concluded that such a clause constituted a covenant by the contractor to pay within a reasonable time, in the absence of payment from the owner. The standard by which the contingent payment clause’s enforceability is to be weighed is that of a reasonable period of time for payment. The determination of what constitutes a reasonable time period is a question of fact. The Midland court declared that a delay in payment from the GC to the subcontractor of more than three years was unreasonable.

The viability of a contingent payment or pay-when-paid clause next was addressed in the unpublished opinion of Envirocorp Well Services, Inc. v. Camp Dresser & McKee, Inc., 2000 WL 1617840 (S.D. Ind. 2000). In this case, the pay-when-paid clause was in an engineer’s subcontract with its consultant and stated that payments would be made to the engineering subconsultant after the engineer received payment from the owner. After noting that no Indiana state court had directly addressed the issue, the federal court reasoned that an Indiana court would conclude that the pay-when-paid clause does not permanently deprive the consultant of its right to payment if the owner refuses to pay the engineer. Rather, citing Midland, the court in Envirocorp concluded that such clauses simply provide the contractor with a reasonable time to obtain payment from the owner before the contractor is contractually bound to the subcontractor for immediate payment.

In a non-Indiana case, Moore Bros. Co. v. Brown & Root, Inc., 207 F.3d 717 (4th Cir. 2000), the GC and its payment bond surety were found liable to the subcontractor for nonpayment even though the subcontract contained a contingent, pay-when-paid clause. The surety was found liable under the bond and was not afforded the defense of the contingent payment clause because the surety had failed to expressly include it in the terms in the bond itself. The bond terms stated that valid claims would be paid if the claimant had not been paid by the contractor within a set number of days, the surety unconditionally promising to pay any claimant who had not been paid in full within 90 days after work was completed for “sums as may be justly due.” The court found that to allow the surety to avoid payment based upon this contingent payment defense would let the surety escape its liability and contravene the purpose of the payment bond, which was to ensure that valid claims of subcontractors and suppliers were paid. In reaching its conclusion, the court cited three other courts that had rejected attempts by sureties to invoke the pay-when-paid defense that is available to the principal-contractor.

The BMD Contractors case

In the recent decision of BMD Contractors, Inc. v. Fidelity and Deposit Company of Maryland, the 7th Circuit Court of Appeals (which covers Indiana) addressed the issue of contingent payments in the context of a suit on a payment bond. In that case, the owner of an automobile transmission manufacturing plant, Getrag Transmission Manufacturing LLC, hired Walbridge Aldinger Company as the GC. Walbridge hired numerous subcontractors, including Industrial Power Systems Inc. to complete mechanical piping work. The Walbridge subcontract included provisions stating that Industrial acknowledged that it was relying upon Getrag’s credit and ability to pay and was further accepting the risk that Getrag may not be able to perform its contract with Walbridge. Industrial subsequently hired BMD Contractors Inc. to perform piping work, who in turn, ordered supplies from another company. Industrial also executed a payment bond with Fidelity and Deposit Company of Maryland, whereby Fidelity was the surety for Industrial’s payment obligations to BMD.

Sometime after construction began, Getrag filed for bankruptcy and, as a result, failed to pay Walbridge. Walbridge subsequently failed to pay Industrial, and Industrial failed to pay BMD. Both BMD and its supplier filed mechanic’s liens, and BMD assigned a portion of its rights under the payment bond to that supplier. After Fidelity refused to pay, BMD and the supplier filed suit on the payment bond.

The District Court found in favor of Fidelity on the basis that its principal, Industrial, was not liable to BMD or its supplier for payment under the pay-if-paid provision in the subcontract. The District Court had determined that the condition precedent language in the subcontract was properly construed as a pay-if-paid provision, even though the subcontract did not include an express provision stating that BMD was assuming the risk of Getrag’s insolvency, as did Walbridge’s subcontract with Industrial. The District Court also determined that the subcontract did not need to be expressly incorporated into the terms of the payment bond, because Fidelity as surety was liable only to the extent that its principal, Industrial, was liable for payment (thereby contravening the prior ruling in Moore).

In affirming the District Court, the 7th Circuit analyzed the provisions of both the payment bond and the subcontract. The bond allowed claimants such as BMD to prosecute claims for such “sums as may be justly due claimant,” so the key question was whether BMD was entitled to payment under the subcontract. The court rejected BMD’s arguments that the conditional language was ambiguous, or for other reasons should be construed as a pay-when-paid clause, which would govern the timing of payment but not the ultimate obligation to pay. The court concluded that the condition precedent language in the subcontract was sufficient to create a pay-if-paid provision under Indiana law. BMD relied upon prior Indiana caselaw, which is often cited for the proposition that Indiana is a pay-when-paid jurisdiction. The court distinguished those cases, noting that the subcontracts at issue did not include condition precedent language such as that included in the subcontract between Industrial and BMD. Based upon this, among other reasons, the court concluded that Fidelity, no less than Industrial, may rely on the pay-if-paid clause in the Industrial-BMD subcontract.

Where we are today and how to negotiate the middle ground

Practically speaking, the BMD case is important as it could lead to Indiana courts (BMD was a federal court applying Indiana law) likewise holding that a contingent payment clause that states the express condition precedent language will be interpreted as a true pay-if-paid clause. This result is not unexpected. Perhaps more important yet is the court’s shifting analysis of the Moore case in the context of the payment bond surety. Moore previously held that where a pay-if-paid clause excuses the GC’s nonpayment, the subcontractor can still recover against the surety. However, the court found Moore “unpersuasive and contrary to basic Indiana surety-law principles” as it cited to three separate cases, each of which were decided after Moore and each of which rejected the position held therein. This means that the payment bond surety will have this same defense to claims as does its principal. Subcontractors are now faced with the risk of true contractual risk shifting on the ability to get paid with no surety recourse likely being available.

So how can the puzzle of the contingent payment provision be solved? First and foremost, a subcontractor will want to strike or at least limit the contingent payment clause in its subcontract. It does not want the contractor’s duty to make progress and final payments absolutely conditioned upon the contractor’s prior receipt of payment from the owner. Terms that take a clause from a timing device to a true pay-if-paid clause thus should be limited. The counterbalancing consideration for the GC is to have some opportunity to ensure that it gets paid first by the owner before its own downstream payment obligations ripen. A middle ground for the subcontractor and GC is to provide that acceptance by the GC of the owner’s tendered payment or unreasonable delay in receipt of payment from the owner will not excuse the contractor’s primary obligation to pay the subcontractor within a set time (for example, 60 or 90 days) after payment otherwise is due and payable. In this fashion, the GC gets more time to ensure that it is paid first, but the subcontractor ultimately has assurance that it will be paid one way or the other. Another option for the parties is to provide for the contractual escrowing of monies – even if limited to retainage – that would be otherwise due and owing, though the GC may not have the financial wherewithal to do this. Notwithstanding the contingent payment clause, from the subcontractor’s perspective, if all else fails, the indebtedness can still be secured through use of the statutory claim remedies (i.e., mechanic’s lien and personal liability notice on a private project, or a payment bond claim and verified statement of claim on a public project).

Regardless of how the negotiations proceed and the type of contingent payment clause that may ultimately be included in the subcontract, it is imperative that the parties have a full understanding of exactly what they are intending with respect to the contingent payment provision. Whether it is the subcontractor’s receipt of payment or the GC’s liability exposure associated with making payments downstream despite not having received payment from the owner, the puzzle of the contingent payment clause could make all the difference on a construction project.•

Mr. Drewry is a partner in Drewry Simmons Vornehm in Indianapolis. He chairs the DTCI Construction Law Section. The opinions expressed in this article are those of the author.

ADVERTISEMENT

Post a comment to this story

COMMENTS POLICY
We reserve the right to remove any post that we feel is obscene, profane, vulgar, racist, sexually explicit, abusive, or hateful.
 
You are legally responsible for what you post and your anonymity is not guaranteed.
 
Posts that insult, defame, threaten, harass or abuse other readers or people mentioned in Indiana Lawyer editorial content are also subject to removal. Please respect the privacy of individuals and refrain from posting personal information.
 
No solicitations, spamming or advertisements are allowed. Readers may post links to other informational websites that are relevant to the topic at hand, but please do not link to objectionable material.
 
We may remove messages that are unrelated to the topic, encourage illegal activity, use all capital letters or are unreadable.
 

Messages that are flagged by readers as objectionable will be reviewed and may or may not be removed. Please do not flag a post simply because you disagree with it.

Sponsored by
ADVERTISEMENT
Subscribe to Indiana Lawyer
  1. It really doesn't matter what the law IS, if law enforcement refuses to take reports (or take them seriously), if courts refuse to allow unrepresented parties to speak (especially in Small Claims, which is supposedly "informal"). It doesn't matter what the law IS, if constituents are unable to make effective contact or receive any meaningful response from their representatives. Two of our pets were unnecessarily killed; court records reflect that I "abandoned" them. Not so; when I was denied one of them (and my possessions, which by court order I was supposed to be able to remove), I went directly to the court. And earlier, when I tried to have the DV PO extended (it expired while the subject was on probation for violating it), the court denied any extension. The result? Same problems, less than eight hours after expiration. Ironic that the county sheriff was charged (and later pleaded to) with intimidation, but none of his officers seemed interested or capable of taking such a report from a private citizen. When I learned from one officer what I needed to do, I forwarded audio and transcript of one occurrence and my call to law enforcement (before the statute of limitations expired) to the prosecutor's office. I didn't even receive an acknowledgement. Earlier, I'd gone in to the prosecutor's office and been told that the officer's (written) report didn't match what I said occurred. Since I had the audio, I can only say that I have very little faith in Indiana government or law enforcement.

  2. One can only wonder whether Mr. Kimmel was paid for his work by Mr. Burgh ... or whether that bill fell to the citizens of Indiana, many of whom cannot afford attorneys for important matters. It really doesn't take a judge(s) to know that "pavement" can be considered a deadly weapon. It only takes a brain and some education or thought. I'm glad to see the conviction was upheld although sorry to see that the asphalt could even be considered "an issue".

  3. In response to bryanjbrown: thank you for your comment. I am familiar with Paul Ogden (and applaud his assistance to Shirley Justice) and have read of Gary Welsh's (strange) death (and have visited his blog on many occasions). I am not familiar with you (yet). I lived in Kosciusko county, where the sheriff was just removed after pleading in what seems a very "sweetheart" deal. Unfortunately, something NEEDS to change since the attorneys won't (en masse) stand up for ethics (rather making a show to please the "rules" and apparently the judges). I read that many attorneys are underemployed. Seems wisdom would be to cull the herd and get rid of the rotting apples in practice and on the bench, for everyone's sake as well as justice. I'd like to file an attorney complaint, but I have little faith in anything (other than the most flagrant and obvious) resulting in action. My own belief is that if this was medicine, there'd be maimed and injured all over and the carnage caused by "the profession" would be difficult to hide. One can dream ... meanwhile, back to figuring out to file a pro se "motion to dismiss" as well as another court required paper that Indiana is so fond of providing NO resources for (unlike many other states, who don't automatically assume that citizens involved in the court process are scumbags) so that maybe I can get the family law attorney - whose work left me with no settlement, no possessions and resulted in the death of two pets (etc ad nauseum) - to stop abusing the proceedings supplemental and small claims rules and using it as a vehicle for harassment and apparently, amusement.

  4. Been on social security sense sept 2011 2massive strokes open heart surgery and serious ovarian cancer and a blood clot in my lung all in 14 months. Got a letter in may saying that i didn't qualify and it was in form like i just applied ,called social security she said it don't make sense and you are still geting a check in june and i did ,now i get a check from my part D asking for payment for july because there will be no money for my membership, call my prescription coverage part D and confirmed no check will be there.went to social security they didn't want to answer whats going on just said i should of never been on it .no one knows where this letter came from was California im in virginia and been here sense my strokes and vcu filed for my disability i was in the hospital when they did it .It's like it was a error . My ,mothers social security was being handled in that office in California my sister was dealing with it and it had my social security number because she died last year and this letter came out of the same office and it came at the same time i got the letter for my mother benefits for death and they had the same date of being typed just one was on the mail Saturday and one on Monday. . I think it's a mistake and it should been fixed instead there just getting rid of me .i never got a formal letter saying when i was being tsken off.

  5. Employers should not have racially discriminating mind set. It has huge impact on the society what the big players do or don't do in the industry. Background check is conducted just to verify whether information provided by the prospective employee is correct or not. It doesn't have any direct combination with the rejection of the employees. If there is rejection, there should be something effective and full-proof things on the table that may keep the company or the people associated with it in jeopardy.

ADVERTISEMENT