Indiana Attorney General Todd Rokita’s Office announced Tuesday that it is taking additional steps to keep both of the coal-fired electric generation units open at the Rockport Generating Station in Spencer County.
In a pair of filings with the Indiana Utility Regulatory Commission, Rokita said his office wants to prevent the commission from treating the planned shutdown of the coal units as final while work on a proposed natural gas-fired plant at the site continues.
The Rockport Generating Station is operated by Fort Wayne-based Indiana Michigan Power, or I&M, a subsidiary of Columbus, Ohio-based AEP.
One of the coal-fired units at the plant, Unit 1, was set to be retired by the end of 2028 as part of a 2019 modification to a consent decree approved by the U.S. District Court for the Southern District of Ohio. The utility also agreed to shut down Unit 2 as part of a separate agreement approved by state regulators in 2021.
In July, Rokita filed a legal challenge to prevent the closure of Unit 1 and was taking other actions to keep Unit 2 running. That litigation remains pending.
In a news release, Rokita said while his office supports the construction of the planned 1,520-megawatt natural gas plant, the state can’t afford to have the coal-fired units shut down when the natural gas plant won’t be operational for years after the fact.
“We’re making sure the IURC doesn’t lock in those retirements or treat the natural-gas plant approval as a green light for early shutdowns,” Rokita said. “My team and I will continue to pursue an all-of-the-above approach — keeping the coal units online as long as needed, supporting the new gas plant, and exploring options like nuclear — which is the best way to hold down utility bills for families, protect Hoosier jobs, and strengthen the reliability of our energy grid.”
I&M announced plans for the proposed natural gas plant, to be known as the Rockport Energy Center, in July. The utility filed for a certificate of public convenience and necessity from the IURC and said it expected a decision in early 2027.
If approved, construction could begin later that year and would be expected to become operational in the summer of 2030, about a year and a half after the coal-fired units were set to close.
Rokita’s office said the 1,520 megawatts of new electric capacity generated by the natural gas plant would not fully replace the existing 2,600 megawatts generated by the coal-fired units, and the multi-year gap before the gas plant comes online “raises serious reliability concerns.”
In its filings, Rokita is asking the IURC to leave retirement-related depreciation, dismantlement and cost-deferral treatment for both units subject to later adjustment based on the outcome of the federal consent-decree litigation; find that any order in those cases does not constitute approval of the retirement of either coal-fired unit; and impose conditions to “preserve resource adequacy between the planned retirements and the gas plant’s in-service dates.”
Indiana Michigan Power did not respond to a request from Inside INdiana Business for comment at deadline Wednesday.
IBJ’s Joey Harris contributed to this story.