Ambrose suit alleges city tried to take stamping plant land for Infosys campus

  • Print
Listen to this story

Subscriber Benefit

As a subscriber you can listen to articles at work, in the car, or while you work out. Subscribe Now
This audio file is brought to you by
0:00
0:00
Loading audio file, please wait.
  • 0.25
  • 0.50
  • 0.75
  • 1.00
  • 1.25
  • 1.50
  • 1.75
  • 2.00

Local developer Ambrose Property Group has leveled new allegations against the city of Indianapolis in a lawsuit it filed Tuesday in the ongoing fight over the company’s decision not to develop the former GM stamping plant site on the western edge of downtown.

The company said in its 28-page complaint that Mayor Joe Hogsett’s administration had threatened to take the site through eminent domain in 2017 — for a campus for tech giant Infosys — two years before its latest threat to use condemnation to buy the land.

Ambrose said the previous dispute, which the company said ended when Infosys took a site at the Indianapolis International Airport, led it to add a clause in its project agreement with the city meant to prohibit the Hogsett administration from pursuing eminent domain in the future.

But now the city is threatening to take the property through eminent domain again — and the lawsuit alleges it could be part of an effort to provide space for Indy Eleven’s proposed soccer stadium development.

The suit also repeats previous allegations that the city’s eminent domain threat has cost Ambrose — which is now trying to sell 91 acres of stamping plant land — millions of dollars and set back its sale of the property.

“We are disappointed it has come to this, but the city’s illegal threats and actions have left us with no option but to protect our rights through a lawsuit,” Ambrose said in a written statement.

Ambrose also is requesting a preliminary injunction to stop the city’s efforts to take the land through eminent domain. That petition included additional details about the dispute.

In a written statement, the city’s chief corporation counsel, Donnie Morgan, said the city does not comment on pending litigation “out of respect for the judicial process.”

The city has not actually filed a lawsuit seeking to take the Ambrose property by eminent domain — although it has taken some initial steps — and Morgan did not indicate whether the city plans to do so.

The suit is likely to deepen the rift that began in September, when Ambrose announced it would not pursue a $1.4 billion development at the stamping plant, which it had named Waterside. The company initially said it was refocusing on e-commerce and industrial projects and away from mixed-use developments. Later, it said the move was spurred by the city’s decision not to award additional incentives to the Waterside project, which Ambrose had expanded.

Throughout its filing, Ambrose maintained the city acted inappropriately in asserting it could use eminent domain to take control of the land — in part because of the language in the February 2018 project agreement that explicitly states the city could not take the land by force.

But Indiana law recognizes eminent domain as a sovereign right, giving the city extensive latitude in such cases.

The company’s litigation comes four weeks after the company filed a tort claim notice  (a precursor to lawsuits) against the city, in which it made allegations of fraud and slander — though neither of those claims are in the actual lawsuit.

“Unfortunately, Waterside will remain a vacant, unused lot until this Court confirms that the City’s plan to take Waterside is unlawful and violates the City’s contract with Ambrose and that Ambrose (or another developer) is therefore free to move forward with bringing Waterside to life,” the lawsuit reads.

Ambrose alleges in the suit that the city had tried to take over part of the stamping plant site in 2017, when Infosys expressed interest in building its expansive new campus on the property.

Ambrose said the city threatened to take at least half the land through eminent domain — after the company rejected the city’s offer of $36.75 million for about 55 acres, citing neighbors’ concerns over the Infosys project.

“The City … intended to cut Ambrose out of any deal with Infosys,” the lawsuit alleges. “The City intended for Browning Investments to handle development of the campus and did not want Ambrose to have any role” in the project.

The suit indicates the city ultimately backed off, after RACER Trust — the GM bankruptcy redevelopment entity that sold the land to Ambrose after an extensive bid process that involved the city — and other entities put pressure on local officials to find a different site for the development. Infosys ultimately settled on the airport site, where construction is now underway.

Ambrose said it asked for the provision forbidding eminent domain because of the Infosys situation.

“That provision was in the contract because the City had previously threatened to take the property, and we needed assurance the City would not try to take it again,” the company’s statement said. “Accordingly, the contract protected us from the City trying to take the land. Based on that promise, we invested millions in the redevelopment of the property.”

The company said it also learned through a public records request that the city is in negotiations with the Indy Eleven to take over the stamping plant site, though it is not indicated in those records that the specific site being discussed is the stamping plant property.

IBJ has also requested documents related to those discussions but has not received the information.

Ambrose said a recent appraisal of the property valued the land “at a conservative $50 million,” but the company has declined to release the appraisal or provide other documents backing up that valuation.

The company said the figure is based solely on the property’s value as-is, not including other outside factors like the agreement with the city, which is worth at least $26.8 million in public infrastructure funding and could be transferred to a new owner.

Ambrose has previously stated it believes the land has fair-market value ranging from $65 million to $100 million, although it has not been willing to provide documentation proving those figures, either.

In late October, the city met with Ambrose officials at the company’s Monument Circle office and floated $6 million for the property, which Ambrose said it rejected.

Ambrose said any progress on the development has stopped amid confusion and the contentious dispute between the company and city officials.

“The city’s unlawful threats have thus frozen all activity at the site because no developer will invest in the property until the city’s threats are removed,” the statement said, in part. “The sooner this dispute is resolved, the sooner our community can begin to reap the benefits of the property’s development. We look forward to a resolution of this matter.”

The site previously was proposed as the location for the Marion County Justice Center, which is now under construction in the Twin Aire neighborhood southeast of downtown.

Please enable JavaScript to view this content.

{{ articles_remaining }}
Free {{ article_text }} Remaining
{{ articles_remaining }}
Free {{ article_text }} Remaining Article limit resets on
{{ count_down }}